Uganda has postponed the start of commercial oil production and crude exports to before the end of June 2027 as supply chain constraints and disruption linked to the Iran war delay essential equipment, OilPrice.com reported. Officials at the Uganda National Oil Company and the Petroleum Authority of Uganda announced the revised timetable, extending the wait for first oil beyond two decades after commercial reserves were discovered in 2006.
The petroleum authority attributed the setback to late deliveries of components for metering, electrical instrumentation and telecommunications. These systems are needed to complete production and export infrastructure. Although officials put construction of the $5.6 billion East African Crude Oil Pipeline at more than 90% complete, pump stations three and four and supporting electrical, telecommunications, instrumentation and security systems remain unfinished.
Commissioning requires co-ordinated testing across the pipeline, Tilenga, Kingfisher and Tanga projects. Lawmakers said in October that Tilenga was 78% complete and Kingfisher 90%, but central processing facilities needed to treat and stabilise crude were still in final installation and pre-commissioning. The 1,443-kilometre heated pipeline, running from western Uganda to Tanzania’s Tanga Port, also needs thermal integration before it can safely transport Uganda’s waxy crude, according to the report.
Initial production is expected at around 25,000 barrels per day from CNOOC’s Kingfisher field, increasing towards its 40,000 bpd capacity. TotalEnergies’ Tilenga project is expected to reach 190,000 bpd, taking combined peak output to about 230,000 bpd. The petroleum authority estimates potential annual government oil income of $1.5 billion-$2.5 billion once production starts. Uganda has an estimated 6.65 billion barrels of oil in place, including about 1.65 billion barrels considered recoverable.
The postponement also threatens budget assumptions. OilPrice.com reported that Finance Minister Henry Musasizi told parliament in June that the Ush84.39 trillion budget for fiscal 2026/2027 included Ush1.44 trillion, or roughly $380 million, in petroleum receipts. S&P Global Ratings has changed the outlook on Uganda’s B- sovereign rating from positive to stable and forecasts a fiscal 2027 deficit of 6% of GDP. It also cut its growth projection for that year to 5.8%, from earlier estimates of 7%-7.5%.